The resettlement

The fourth page accompanying the timeline: the years in which the Bicaz dam changed the valley. See also Lake Izvorul Muntelui and The villages under the lake.

The plan

The country’s electrification plan provided for a 220 MW hydroelectric plant on the Bistrița, at Stejaru, fed through a tunnel from a reservoir. The dam was to hold back the waters over 33 km and about 3,100 hectares – almost the entire valley floor of the old Hangu region.

The expropriation

By a decree of 31 May 1957, 3,070.79 hectares were expropriated in six communes: Bicaz, Izvorul Alb, Ceahlău, Hangu, Poiana Teiului and Galu. People could receive land in exchange, up to 5 hectares, and a cash allowance to rebuild their household. The people of Hangu say that those moved first were better compensated, while for the others a sum of 16,000 lei was fixed, whatever they lost; some received nothing.

The move

The resettlement took place in 1959–1960. The villages of Poienari, Hangu, Fârțâgi and Lețești were moved entirely; Secu, Ruginești, Buhalnița, Izvorul Alb, Audia, Răpciuni, Schit and Bistricioara in part. From the whole lake area 2,291 households left, with 18,760 people. Of these, 13,196 chose to stay close to their old homes and moved their houses up the slopes, where they had hay meadows.

Churches and cemeteries

The last service in the reinforced-concrete church of Gura Hangului, finished only in 1951, was held by the priest Mihai Coroamă on 21 May 1959. The church was then demolished with explosives; its ruins can be seen when the water is low. The old church, of 1829, and the bell tower were taken to Chirițeni, together with the cemetery. The iconostasis, icons and pews of the new church were given to the parish of Pângărăcior; the bells from Răpciuni went to Schitișor, and its iconostasis and pews to the cathedral in Rădăuți.

The lake and the new centre

In 1960 the gates of the dam were lowered and the water covered the valley, forming a lake 35 km long and at most 2 km wide. The new centre of the commune was built in haste, at Audia, without a plan, partly with materials from demolished buildings. The post office was set up in 1960, and the new school building opened in 1964. The mayors in those years were Constantin Caia (1955–1960) and Constantin Iftinca (1960–1966). The author notes that many people of Hangu experienced the resettlement as an injustice and that the compensation did not cover what was lost.

Source: Gheorghe Drugă, “Istoria Hangului”, Editura Cetatea Doamnei, Piatra-Neamț, 2007 (summary).

Previous period: The modern commune · Timeline · Next period: Hangu after 1989